9 floor Office Block-Only pergola
beam remaining
 

 


Office Block –Work in progress
on 16th floor
 

 


Retail Block- Work in progress
second floor slab onwards
 

 

 


Retail Area: RCC work in Second
Floor Level Slab is in progress

 


RCC work to 15th Floor Level
Slabis progress Shuttering work
to 10th Floor Level Slab is in progress

 

 


Retail Area: RCC work in First
Floor Level Slab is in progress

 


North Side View showing RCC
work in columns from 8th Floor to
9th Floor is in progress.

 


Front view showing RCC work in
Columns from 8th Floor to 9th Floor
Level in Tower Area (19 storeyed) and
Reinforcement work at 7th Floor Level
Slab in Tower Area (9 storeyed) is in
progress.

 

 


Front view showing R C C work in
Columns from 6th Floor to 7th Floor
in Tower Area (9 storeyed) and from
7th Floor to 8th Floor in Tower Area
(19 storeyed) is in progress

 


Multiple activities in Retail and
Tower Area are in progress


 

 


Shuttering work at First Floor
Level Slab in Retail Area is
in progress

 

 


Front view showing Shuttering
work at 7th Floor Level Slab in
Tower Area (9 storeyed) and from
R C C work at 8th Floor Level Slab
in Tower Area (19 storeyed)
is in progress

 


Rear View showing the scaffolding
arrangement for Block/Brick work
started from Ground Floor in
Tower Area.

 

 


Shuttering work at First Floor
Level Slab in Retail Area
is in progress