Construction Updates

 


Tower 2A –Basement Roof Slab
completed. Stilt floor roof slab
shuttering in progress.

 


Tower 3A – 2nd Floor Roof Slab
Completed. 3rd Floor Roof Slab
Shuttering Progress

 


Tower 3B – 5th Floor roof slab
completed. 6th Floor column
casting in progress.

 


Tower 3C – 5th Floor Roof Slab
Completed. 6th Floor Roof Slab
R/F in Progress.

 


Tower 3D – 1st Floor Slab
completed. 2nd floor roof slab
shuttering in Progress.

 


Tower 3E – Basement Roof Slab
completed. Stilt Floor Roof slab
shuttering in progress.

 


Tower 3F – 2nd Floor Roof Slab
completed. 3rd Floor Roof Slab
shuttering in progress.

 


Tower 3G - Stilt Floor Roof Slab
completed. 1st Column casting
in progress.

 


Tower 3H – 1st Floor Roof Slab
completed. 2nd Floor Roof Slab
R/F in progress.

 


Tower 3I - Basement Roof Slab
completed. Stilt Floor Column
casting in progress.

 


Tower 3J - Basement Roof Slab
shuttering in progress.

 


Tower 4i - Basement Roof Slab
shuttering in progress.

 


Tower 2A: RCC Work in Raft
Foundation is in Completed
 

 


Tower 3A: Shuttering work at
Ground Floor level slab is in
progress.

 


Tower 3B: Shuttering work at
First Floor Level Slab is in Progress.

 


Tower 3C: RCC work in slab at
First Floor level in is Completed

 


Tower 3D: Shuttering work in slab
at Ground Floor Level is in progress.

 


Tower 3E: RCC work in Columns
from Raft Foundation to Ground
Floor Slab of is in Progress.

 


Tower 3F: Reinforcement work in
Raft Foundation of is in Progress.

 


Tower 3G: Excavation of Lift Pit
in Raft Foundation of is in Progress.

 


Tower 3H: RCC work Under Raft
Foundation of is in Progress

 


Reinforcement Work in Raft
Foundation in Tower 2A, Aster
Court, is in Progress
 

 


RCC work in Columns from Raft
Foundation to Ground Floor level
slab in Tower 3 A, Aster Court
is completed

 


RCC work in slab at Ground
Floor level in Tower 3 B,
Aster Court is Completed
 

 


Shuttering work in slab at First
Floor level in Tower 3 C,
Aster Court is in Progress
 

 


RCC work in columns from Raft
Foundation to Ground Floor,
Aster Court, is in progress
 

 


R C C work in Columns from
Raft Foundation to Ground
Floor Slab of Tower 3 E, Aster
Court, is in Progress

 


Reinforcement work in Raft
Foundation of Tower 3 F,
Aster Court, is in Progress

 


R C C Work in Raft Foundation
in Tower 2A, Aster Court, is in
Progress

 


Shuttering work at Ground Floor
level slab in Tower 3 A, Aster
Court is in progress

 


R C C work in Columns from
Ground Floor to First Floor in
Tower 3 B, Aster Court is in Progress

 


R C C work in slab at First Floor
level in Tower 3 C, Aster Court
is in Progresss

 


Shuttering work in slab at Ground
Floor Level in Tower 3 D, Aster
Court, is in progress

 


R C C work in Columns from Raft
Foundation to Ground Floor Slab of
Tower 3 E, Aster Court, is in Progress

 


Reinforcement work in Raft
Foundation of Tower 3 F, Aster
Court, is in Progress